January 30, 2026 • The Telephone Building
Crews begin streetscape improvements by removing worn and damaged pavers along the Telephone Building.
Read moreJanuary 29, 2026 • Peoples Bank
Templates mark the future footprint of key exterior elements at the Peoples Bank building.
Read moreJanuary 26, 2026 • Peoples Bank
A water-resistant coating is applied to the Peoples Bank building as part of ongoing exterior restoration.
Read moreJanuary 14, 2026 • Peoples Bank
Metal support brackets are being installed inside the west wall window openings at the Peoples Bank building in preparation for specialty glass installation.
Read moreJanuary 12, 2026 • Peoples Bank
Progress continues at the Peoples Bank building with the arrival of large, specialty glass panels for the west wall.
Read moreJanuary 8, 2026 • Peoples Bank
Work at the east entry of the Peoples Bank building advances, bringing the exterior closer to its finished historic appearance.
Read moreJanuary 1, 2026 • Peoples Bank
The south side of the Peoples Bank building is progressing with plastering and waterproofing.
Read moreDecember 26, 2025 • Peoples Bank
Behind-the-scenes work is underway to protect the Peoples Bank building from future water intrusion.
Read moreDecember 25, 2025 • F.W. Woolworth Co.
Exterior lighting installation brings a finished look to the Woolworth building’s storefront.
Read moreDecember 14, 2025 • F.W. Woolworth Co.
Painters applied the final dark green coat to the Woolworth Building’s southwest entryway, completing the historically inspired finish around the windows and doors.
Read moreDecember 13, 2025 • F.W. Woolworth Co.
Crews installed new period-style windows along the west side of the Woolworth building, securing each unit and sealing them for long-term protection.
Read moreDecember 10, 2025 • F.W. Woolworth Co.
The removal of west-side windows marks another step in the Woolworth building restoration.
Read moreDecember 9, 2025 • F.W. Woolworth Co.
Crews prepared the Woolworth building’s southwest entryway for paint by completing trim, sealing gaps and creating an even surface for the upcoming finish.
Read moreDecember 6, 2025 • F.W. Woolworth Co.
Crews installed a white membrane roof on the northwest awning facing Cleveland Street, adding a reflective “cool roof” surface above the future restaurant entrance.
Read moreNovember 30, 2025 • Peoples Bank
Chalk lines now mark the layout for the mosaic tile façade at the Peoples Bank building.
Read moreNovember 28, 2025 • F.W. Woolworth Co.
Awning specialists installed the southwest awning frame at the Woolworth building.
Read moreNovember 25, 2025 • F.W. Woolworth Co.
New paint and trim detailing now highlight the Woolworth building’s historic sign and façade.
Read moreNovember 4, 2025 • F.W. Woolworth Co.
The Woolworth building’s façade gets a fresh finish, highlighting the craftsmanship of its 1928 architecture.
Read moreOctober 31, 2025 • F.W. Woolworth Co.
Scaffolding is up at the Woolworth building’s south side where crews apply stucco to the wall.
Read moreOctober 28, 2025 • F.W. Woolworth Co.
Crews complete exterior painting along the Woolworth building’s west wall, achieving a smooth, uniform finish that protects and enhances the façade.
Read more