August 5, 2025 • 600 Block
After stripping drywall and stucco, demolition crews removed the entire wood framing system inside 635 Cleveland Street.
Read moreAugust 1, 2025 • 600 Block
The recessed back entry at 635 Cleveland is demolished, opening up more usable space under the former mezzanine.
Read moreJuly 27, 2025 • 600 Block
Old ducts and compressors are gone as another 600 Block structure is prepared for renewal.
Read moreCrews remove non-load-bearing steel support columns from the interior of 635 Cleveland Street, clearing the way for layout preparation and framing in the next stage of transformation.
Read moreJuly 17, 2025 • 600 Block
Crews remove all fiberglass insulation from 639 Cleveland Street as part of the full interior demolition, clearing the way for sustainable material upgrades in the building’s renovation phase.
Read moreJuly 13, 2025 • 600 Block
Crews remove the floor tile at 623 Cleveland Street to expose the subfloor and allow for detailed architectural assessments ahead of interior layout design.
Read moreJuly 9, 2025 • 600 Block
Crews remove ceramic floor tile at 635 Cleveland Street, exposing the underlying concrete slab in preparation for finish work.
Read moreJuly 5, 2025 • 600 Block
Crews remove the back structure and all of the remaining studs at 635 Cleveland Street.
Read moreJuly 1, 2025 • 600 Block
Crews remove the outer brick from the chimney, uncovering the original brickwork.
Read moreJune 26, 2025 • 600 Block
Crews remove all non-load-bearing studs inside 639 Cleveland Street, preparing for new framing and future renovations.
Read moreCrews remove the outdated tile floor inside 629 Cleveland Street, setting the stage for upcoming renovation work.
Read moreJune 17, 2025 • 600 Block
All bathrooms and plumbing systems are removed at 635 Cleveland Street, clearing the way for installation of new copper plumbing.
Read moreJune 12, 2025 • 600 Block
During interior demolition at 635 Cleveland Street, crews removed old carpet, exposing the concrete slab beneath.
Crews removed the old carpet from 629 Cleveland Street, uncovering the original tile floor beneath as part of early stage demolition.
AC coils were removed at 639 Cleveland Street and refrigerant was recovered at 645, completing an environmentally responsible phase of demolition.
After extensive interior demolition, the lead architect conducted a full walkthrough of the 600 Block to document exposed structural features and finalize the restoration plans.
Read moreCrews completed safe refrigerant removal from 629 Cleveland Street’s HVAC systems, preventing environmental release and clearing the way for sustainable upgrades.
Read moreDemolition crews uncover a heavy safe inside 645 Cleveland Street, dating back to the early 1900s and adding a new layer of discovery to the ongoing renovation.
Read moreCrews uncovered signs of a long-forgotten fire during interior demolition at 635 Cleveland Street, revealing burn marks and charred framing above the ceiling and on the walls.
Read moreMarch 11, 2025 • 600 Block
Demolition crews at 639 Cleveland remove walls and finishes, revealing unexpected steel framing and a patchwork of materials beneath.
Read more