August 16, 2025 • Peoples Bank
Chalk lines and spray paint are used to mark the wall locations at Peoples Bank, starting the framing work.
Read moreAugust 12, 2025 • Peoples Bank
Second-floor copper water lines are being installed at the Peoples Bank building with a press-fit system for secure, efficient connections.
Read moreAugust 7, 2025 • Peoples Bank
Plumbers have started rough-in work on the second floor of the Peoples Bank, following the completion of underground lines. Crews are dry-fitting pipes and preparing for final connections.
Read moreJuly 21, 2025 • Peoples Bank
Following two months of repair, the scaffolding and overhead protection at the historic Peoples Bank building has been removed, revealing its refreshed exterior and returning its full visual presence to Cleveland Street.
Read moreCrews complete second-floor decking repairs at the Peoples Bank building, leveling the trusses and installing new materials.
Read moreJuly 12, 2025 • Peoples Bank
Window bucks are being installed at the Peoples Bank building, setting the stage for new windows as part of the ongoing restoration.
Read moreJuly 8, 2025 • Peoples Bank
Crews complete critical wall preparation at the Peoples Bank Building, covering the brick face with mortar in advance of waterproofing and stucco installation.
Read moreCrews pour a concrete slab around the installed grease traps at the Peoples Bank building, completing another key step in the building’s infrastructure work.
Read moreJune 30, 2025 • Peoples Bank
Crews reinforce the exposed west wall of the Peoples Bank building with concrete blocks and begin framing new utility corridors.
June 25, 2025 • Peoples Bank
Structural steel installation is completed inside the historic Peoples Bank building, reinforcing the structure.
Read moreGrease traps installation completes beneath the ground-floor slab at the Peoples Bank building.
Read moreJune 15, 2025 • Peoples Bank
The elevator shaft at Peoples Bank was fully rebuilt with reinforced concrete block walls and a new foundation.
Read moreJune 13, 2025 • Peoples Bank
The east wall of the Peoples Bank building is rebuilt using reinforced concrete blocks.
Read moreA portion of the roof at Peoples Bank was removed and replaced with angled planks and sheathing, both of which encourage proper stormwater drainage.
Read moreMay 28, 2025 • Peoples Bank
Crews are rebuilding a section of the east wall at Peoples Bank, reinforcing its foundation and preparing it to support key upper-level architectural elements.
Read moreNew underground plumbing has been installed at the Peoples Bank building, including piping for restrooms, clearing the way for slab preparations and future tenant-ready infrastructure.
Read moreCarpenters reinforced the interior structure of the Peoples Bank to preserve its framework as restoration continues.
Read moreMay 16, 2025 • Peoples Bank
Crews exposed sections of the foundation and slabs at Peoples Bank, reinforcing them with mesh and rebar as part of the ongoing renovation.
Read moreMay 12, 2025 • Peoples Bank
Crews complete vertical saw cutting into the east wall’s second-floor façade in preparation for upcoming demolition work.
Read moreCrews reconstruct the elevator pit at Peoples Bank, deepening and reinforcing the original foundation to support the new elevator shaft.
Read more