November 15, 2025 • Peoples Bank
Vital prep work begins for the modern elevator inside the historic Peoples Bank building.
Read moreNovember 13, 2025 • Peoples Bank
Electricians install conduit and wiring across the Peoples Bank building’s second floor, preparing for lighting and outlets.
Read moreNovember 11, 2025 • Peoples Bank
A smooth floor surface takes shape as crews complete the concrete pour at the Peoples Bank building.
Read moreNovember 9, 2025 • Peoples Bank
Crews install historically accurate second-floor windows at the Peoples Bank building, combining authentic design with modern performance in a major step toward the project’s completion.
Read moreNovember 7, 2025 • Peoples Bank
Step by step, the Peoples Bank restoration moves forward with precise window framing and sealing.
Read moreNovember 3, 2025 • Peoples Bank
Crews install flexible metal conduit and wiring throughout the Peoples Bank building, routing lines for lighting and outlets as part of the electrical rough-in phase.
Read moreOctober 29, 2025 • Peoples Bank
New window units arrive at the Peoples Bank building, ready for installation.
Read moreOctober 25, 2025 • Peoples Bank
Stairwell demolition makes way for framing that will support the second-floor offices at the Peoples Bank building.
Read moreOctober 21, 2025 • Peoples Bank
The Peoples Bank building’s interior air system takes shape with new insulated ductwork.
Read moreOctober 19, 2025 • Peoples Bank
Crews at the Peoples Bank building are preparing window openings for the installation of historically accurate replacements.
Read moreOctober 16, 2025 • Peoples Bank
At the Peoples Bank building, crews are completing ductwork installation across the second floor.
Read moreOctober 13, 2025 • Peoples Bank
Plumbing crews route copper piping from the first to the second floor at the Peoples Bank building, readying the full plumbing system.
Read moreOctober 11, 2025 • Peoples Bank
The team installs wood door bucks throughout the Peoples Bank building—essential framing that sets the stage for precision door work.
Read moreOctober 8, 2025 • Peoples Bank
Electricians are running conduit through first-floor framing at the Peoples Bank building, connecting to future electrical closets as part of the building’s interior wiring plan.
Read moreOctober 4, 2025 • Peoples Bank
Framing crews complete all interior metal framing at the Peoples Bank building, establishing a strong structure for the next stage of wall construction.
Read moreOctober 2, 2025 • Peoples Bank
HVAC crews lifted AC units onto the roof of the Peoples Bank building, paving the way for modern system installation.
Read moreOctober 1, 2025 • Peoples Bank
Crews construct the recessed east entry of the Peoples Bank building with reinforced concrete block and cement.
Read moreSeptember 28, 2025 • Peoples Bank
Crews at the Peoples Bank building extended electrical systems to the back of the property, connecting interior upgrades with exterior service panels to complete a major step in restoration.
Read moreSeptember 26, 2025 • Peoples Bank
HVAC crews at the Peoples Bank building are cutting and installing ductwork sections on the second floor that will support the building’s future air system.
Read moreSeptember 24, 2025 • Peoples Bank
Crews at the Peoples Bank building are preparing to install junction boxes and wiring as part of the second floor electrical utility installation.
Read more