See daily progress on Historic Cleveland Street
Plywood forms enclose exposed sections of the concrete masonry walls at 629–633 Cleveland Street, creating secure areas for the upcoming concrete placement.
Read moreSite preparation continues on the 600 block as crews remove the existing concrete slab at 645 Cleveland Street, creating a clear path for future construction.
Read moreAugust 4, 2026 • 600 Block
Heavy equipment clears existing concrete footings at 645 Cleveland Street, preparing the site for the next phase of redevelopment within the 600 block.
Read moreDemolition crews clear masonry debris at 639 Cleveland Street, preparing the site for reconstruction with updated materials and modern building standards.
Read moreAugust 2, 2026 • 600 Block
Careful demolition work is underway as selected wall sections are removed to prepare 629–633 Cleveland Street for the next phase of construction.
Read moreAugust 1, 2026 • 600 Block
At the base of the masonry walls, anchoring material secures new reinforcing bars before the wall cells are completed.
Read moreThe interior structure at 639 Cleveland Street continues to evolve as demolition crews clear existing elements for future work.
Read moreJuly 30, 2026 • 600 Block
Crews remove structural stair connections inside 639 Cleveland Street, separating existing steel components as interior demolition prepares the building for redevelopment.
Read moreJuly 29, 2026 • 600 Block
Another visible milestone takes shape on the 600 Block. At 639 Cleveland Street, east wall removal creates new views into the building.
Read moreCrews remove a concrete column from the front façade of 639 Cleveland Street, clearing the structure for continued redevelopment and future improvements.
Read moreJuly 26, 2026 • 600 Block
Demolition findings at 629–633 Cleveland Street reveal hidden wall conditions, leading to targeted reinforcement work that strengthens the building’s future structure.
Read moreYears of patched and deteriorated concrete are being removed as the Peoples Bank Building restoration continues to transform the streetscape.
Read moreJuly 20, 2026 • 600 Block
A crane-assisted operation removes a concealed 45-foot steel beam from the 639 Cleveland Street façade, advancing demolition and preparing the building for its next phase of work.
Read moreCrews at 639 Cleveland Street have exposed the existing metal decking after removing the previous roof materials, allowing the team to prepare the surface for the next phase of roof installation.
Read moreFaçade demolition at 639 Cleveland Street reveals a concealed steel support beam, documenting original construction methods.
Read moreJuly 9, 2026 • 600 Block
Preparations continue inside 639 Cleveland Street as crews install structural shoring before the next phase of demolition.
Read moreJuly 8, 2026 • 600 Block
Professional surveyors are documenting the 600 block’s topography and underground utilities, providing the precise site data needed to advance the next phase of redevelopment.
Read moreJuly 7, 2026 • 600 Block
Crews are stabilizing 623–627 Cleveland Street with temporary shoring, creating a safe foundation for the next phase of construction.
Read moreJuly 6, 2026 • 600 Block
Forklifts, trucks and neatly stacked masonry units show the 600 block moving steadily through its renovation sequence.
Read moreJuly 3, 2026 • 600 Block
Crews remove sections of the concrete floor slab at 629–633 Cleveland Street to prepare for underground plumbing installation.
Read more