See daily progress on Historic Cleveland Street
August 26, 2026 • 600 Block
Structural grout is placed within the reconstructed rear masonry wall at 623–627 Cleveland Street, surrounding the previously installed steel reinforcement as wall reconstruction advances.
Read moreAugust 25, 2026 • 600 Block
Wall preparation continues at 623–627 Cleveland Street as crews install and brace temporary plywood panels along the existing masonry walls.
Read moreAugust 24, 2026 • 600 Block
Compact equipment and hand tools are being used to carefully return soil around newly installed underground piping at 629–633 Cleveland Street.
Read moreFollowing preparation of the wall channels, workers assemble vertical reinforcing cages and secure the bars with ties and structural anchoring adhesive at 623–627 Cleveland Street.
Read moreAugust 22, 2026 • 600 Block
Reinforcing steel is being sized and prepared at 623–627 Cleveland Street as crews continue assembling the materials needed for the wall work.
Read moreAugust 21, 2026 • 600 Block
Brick and concrete block are being separated and removed from sections of the existing front wall as preparation work continues at 623–627 Cleveland Street.
Read moreAugust 20, 2026 • 600 Block
Following trench excavation, crews are beginning installation of the underground plumbing system that will support the renovated building.
Read moreExcavation work begins behind 629–633 Cleveland Street as crews prepare trenches for new underground plumbing.
Read moreAugust 18, 2026 • 600 Block
Newly opened masonry channels at 623–627 Cleveland Street receive steel reinforcing bars as crews prepare the walls for the next stage of construction.
Read moreAugust 17, 2026 • 600 Block
Masons rebuild the back wall at 623–627 Cleveland Street with new concrete masonry units, restoring the structure to its planned configuration.
Read moreAugust 16, 2026 • 600 Block
The next phase of interior preparation continues at 623–627 Cleveland Street as crews trench the slab for underground plumbing.
Read moreWorkers remove masonry between existing wall cuts at 623–627 Cleveland Street, creating vertical channels to prepare the structure for the next phase of redevelopment work.
Read moreAugust 14, 2026 • 600 Block
Structural preparation continues at 623–627 Cleveland Street as crews create reinforcement channels within the existing masonry walls.
Read moreAugust 13, 2026 • 600 Block
The removal of existing floor materials is revealing the underlying conditions at 635 Cleveland Street as site preparation moves forward.
Read moreAugust 12, 2026 • 600 Block
Controlled demolition continues at 623–627 Cleveland Street as crews clear existing concrete elements to prepare the foundation area for future work.
Read moreAugust 11, 2026 • 600 Block
Masons install new lintels above wall openings at 629–633 Cleveland Street while rebuilding surrounding concrete block to integrate the structural supports.
Read moreAugust 10, 2026 • 600 Block
Temporary forms come down at 629–633 Cleveland Street as crews patch infill openings and finish the newly reinforced concrete masonry walls.
Read moreAugust 9, 2026 • 600 Block
Selective slab removal at 623–627 Cleveland Street prepares the building frontage for a new façade configuration and recessed storefront entry.
Read moreThe removal of existing masonry columns opens the frontage of 623–627 Cleveland Street and clears the way for the next phase of improvements.
Read moreThe walls at 629–633 Cleveland Street are becoming solid-filled structural assemblies as crews carefully control the concrete placement.
Read more