Crews are placing steel reinforcing bars into vertical channels cut into the masonry walls at 623–627 Cleveland Street. The bars are positioned within the newly prepared sections, where they will be integrated with the existing masonry.
The installation follows the cutting and chipping of the wall channels, adding new structural components to the existing wall system as redevelopment continues.
Learn more about the renovation plans for the 600 block.
October 2, 2026 • 600 Block
October 1, 2026 • 600 Block
September 30, 2026 • 600 Block
September 29, 2026 • 600 Block
September 28, 2026 • 600 Block
September 27, 2026 • 600 Block
September 26, 2026 • 600 Block
September 25, 2026 • 600 Block
September 24, 2026 • 600 Block
September 23, 2026 • 600 Block
See daily progress on Historic Cleveland Street