Get updates as new projects and events unfold
Receive updates on new developments, events and announcements as they happen.
A confirmation email has been sent to your inbox. If you do not receive it shortly, please check your spam or junk folder.
August 18, 2026 • 600 Block
Crews are placing steel reinforcing bars into vertical channels cut into the masonry walls at 623–627 Cleveland Street. The bars are positioned within the newly prepared sections, where they will be integrated with the existing masonry.
The installation follows the cutting and chipping of the wall channels, adding new structural components to the existing wall system as redevelopment continues.
Learn more about the renovation plans for the 600 block.
August 16, 2026 • 600 Block
August 15, 2026 • 600 Block
August 14, 2026 • 600 Block
August 13, 2026 • 600 Block
August 12, 2026 • 600 Block
August 10, 2026 • 600 Block
August 9, 2026 • 600 Block
August 8, 2026 • 600 Block
See daily progress on Historic Cleveland Street