November 10, 2026 • 600 Block

Front Wall Footing Work Advances at 639 Cleveland Street

Worker positions reinforcing bar in footing area.
A worker positions a reinforcing bar within the prepared footing area at 639 Cleveland Street.

Following excavation and forming, crews are installing reinforcing steel for the front wall footing at 639 Cleveland Street. Workers are cutting, assembling and tying the rebar within the prepared footing area. This steel framework will be inspected before concrete is poured, marking another step in preparing the foundation for the reconstructed front wall.

Worker ties reinforcing steel in front wall footing.
A worker ties reinforcing steel within the prepared front wall footing.

Learn more about the redevelopment plans for the 600 block.

Restoration Updates

See daily progress on Historic Cleveland Street