July 21, 2025 • Peoples Bank
Following two months of repair, the scaffolding and overhead protection at the historic Peoples Bank building has been removed, revealing its refreshed exterior and returning its full visual presence to Cleveland Street.
Read moreJuly 20, 2025 • F.W. Woolworth Co.
Crews complete interior steel installation at the F. W. Woolworth Co. building, forming the framework for new roof trusses and stabilizing the structure in preparation for roof construction.
Read moreCrews are removing interior wood and stucco walls at the Brown Brothers Building, thus clearing the way for structural assessment and future reconstruction.
Read moreJuly 18, 2025 • The Telephone Building
Rubber flooring is installed throughout the Telephone Building’s rear stairwell, enhancing safety and appearance.
Read moreJuly 17, 2025 • 600 Block
Crews remove all fiberglass insulation from 639 Cleveland Street as part of the full interior demolition, clearing the way for sustainable material upgrades in the building’s renovation phase.
Read moreCrews complete second-floor decking repairs at the Peoples Bank building, leveling the trusses and installing new materials.
Read moreJuly 15, 2025 • Brown Brothers
Crews remove 26 second-floor doors from the Brown Brothers Building. Each door is labeled for restoration and future relocation.
Read moreJuly 14, 2025 • F.W. Woolworth Co.
Work is progressing at the historic F.W. Woolworth Co. building with the start of construction of the storefront soffit, the horizontal ceiling enclosures above each recessed storefront entrance.
Read moreJuly 13, 2025 • 600 Block
Crews remove the floor tile at 623 Cleveland Street to expose the subfloor and allow for detailed architectural assessments ahead of interior layout design.
Read moreJuly 12, 2025 • Peoples Bank
Window bucks are being installed at the Peoples Bank building, setting the stage for new windows as part of the ongoing restoration.
Read moreJuly 11, 2025 • F.W. Woolworth Co.
Crews are installing new second-floor steel beams at the Woolworth building, which is a major structural phase that supports the future roof restoration.
Read moreJuly 10, 2025 • Brown Brothers
Crews cut down old fiberglass-lined ducts inside the Brown Brothers Building, taking big steps toward a modern HVAC setup.
Read moreJuly 9, 2025 • 600 Block
Crews remove ceramic floor tile at 635 Cleveland Street, exposing the underlying concrete slab in preparation for finish work.
Read moreJuly 8, 2025 • Peoples Bank
Crews complete critical wall preparation at the Peoples Bank Building, covering the brick face with mortar in advance of waterproofing and stucco installation.
Read moreJuly 7, 2025 • The Telephone Building
Custom-stained oak wainscoting and crown molding are installed in the historic lobby of the Telephone Building, reinforcing the building’s original architectural character.
Read moreJuly 6, 2025 • F.W. Woolworth Co.
Crews remove the south parapet at the F.W. Woolworth Building to make way for a structural bond beam.
Read moreJuly 5, 2025 • 600 Block
Crews remove the back structure and all of the remaining studs at 635 Cleveland Street.
Read moreCrews pour a concrete slab around the installed grease traps at the Peoples Bank building, completing another key step in the building’s infrastructure work.
Read moreJuly 3, 2025 • Brown Brothers
Crews remove large sections of wood framing inside the Brown Brothers Building, clearing the way for structural upgrades.
Read moreJuly 2, 2025 • F.W. Woolworth Co.
Crews are removing temporary interior shoring from the first and second floors of the Woolworth Building.
Read more