September 8, 2025 • F.W. Woolworth Co.
Raised wood curbs installed on the Woolworth Building roof will secure skylights and improve efficiency.
Read moreSeptember 7, 2025 • Peoples Bank
The roof replacement at the Peoples Bank begins with the arrival of key materials.
Read moreSeptember 6, 2025 • Brown Brothers
The first-floor cleanout of demolition debris at the Brown Brothers Building is underway, preparing the space for restoration.
Read moreSeptember 5, 2025 • F.W. Woolworth Co.
Restoration continues at the Woolworth Building as parapet sheathing creates a base for fresh stucco.
Read moreSeptember 4, 2025 • 600 Block
The interior floor slab at 635 Cleveland Street is demolished and removed to clear the ground floor.
Read moreSeptember 3, 2025 • Peoples Bank
Metal framing is installed around the structural beams at the Peoples Bank building, adding strength and preparing the walls for upcoming finishing procedures.
Read moreSeptember 2, 2025 • F.W. Woolworth Co.
Original bricks are being reset into Woolworths front parapet with fresh mortar, bringing the parapet back to its historical proportions.
Read moreSeptember 1, 2025 • Peoples Bank
Boyd’s Clocks secured the historic clock brackets to the Peoples Bank, ensuring long-term stability for the landmark feature.
August 31, 2025 • 600 Block
The kitchen hood and ductwork at 635 Cleveland Street have been removed, preparing the space for renovation.
Read moreRestoration continues at the Woolworth Building as crews remove parapet bricks by hand and set them aside for reuse.
Read moreCrews are clearing away demolition debris into a 30-yard dumpster at the Brown Brothers Building.
Read moreAugust 28, 2025 • Peoples Bank
Crews at the Peoples Bank building completed electrical installation by placing junction and outlet boxes on new framing.
Read moreAugust 27, 2025 • F.W. Woolworth Co.
Crews completed installation of roof decking at the Woolworth building, replacing trusses and preparing for an upgraded roof system.
Read moreRestoration of the Brown Brothers Building uncovers original brick walls on the second floor.
Read moreAugust 25, 2025 • 600 Block
Structural truss removal marks a major interior demolition milestone in the renovation of 635 Cleveland Street.
Read moreAugust 24, 2025 • Peoples Bank
Plumbing crews installed a cast-iron storm drainage system at the Peoples Bank building, ensuring reliable water runoff management for the restored landmark.
Read moreAugust 23, 2025 • Brown Brothers
Crews remove the north-side lath-and-plaster walls on the second floor of the Brown Brothers Building, revealing an earlier construction method tougher than drywall.
Read moreWooden trusses are lifted by crane and secured atop the Woolworth building, preparing the structure for decking and installation of a durable waterproof roof.
Read moreAugust 21, 2025 • 600 Block
Crews removed sections of brick at 635 Cleveland Street to examine the building’s integrity, revealing structural concerns that require stabilization.
Read moreAugust 20, 2025 • Peoples Bank
Metal framing crews are making rapid progress at the Peoples Bank building, with wall structures taking shape on both the first and second floors.
Read more