Restoration continues at the Woolworth Building as crews remove parapet bricks by hand and set them aside for reuse.
Read moreCrews are clearing away demolition debris into a 30-yard dumpster at the Brown Brothers Building.
Read moreAugust 28, 2025 • Peoples Bank
Crews at the Peoples Bank building completed electrical installation by placing junction and outlet boxes on new framing.
Read moreAugust 27, 2025 • F.W. Woolworth Co.
Crews completed installation of roof decking at the Woolworth building, replacing trusses and preparing for an upgraded roof system.
Read moreRestoration of the Brown Brothers Building uncovers original brick walls on the second floor.
Read moreAugust 25, 2025 • 600 Block
Structural truss removal marks a major interior demolition milestone in the renovation of 635 Cleveland Street.
Read moreAugust 24, 2025 • Peoples Bank
Plumbing crews installed a cast-iron storm drainage system at the Peoples Bank building, ensuring reliable water runoff management for the restored landmark.
Read moreAugust 23, 2025 • Brown Brothers
Crews remove the north-side lath-and-plaster walls on the second floor of the Brown Brothers Building, revealing an earlier construction method tougher than drywall.
Read moreWooden trusses are lifted by crane and secured atop the Woolworth building, preparing the structure for decking and installation of a durable waterproof roof.
Read moreAugust 21, 2025 • 600 Block
Crews removed sections of brick at 635 Cleveland Street to examine the building’s integrity, revealing structural concerns that require stabilization.
Read moreAugust 20, 2025 • Peoples Bank
Metal framing crews are making rapid progress at the Peoples Bank building, with wall structures taking shape on both the first and second floors.
Read moreAugust 19, 2025 • F.W. Woolworth Co.
Masons have laid concrete block and begun installing the brick façade on the Woolworth building, ensuring it matches the historic appearance of the structure.
Read moreAugust 18, 2025 • Brown Brothers
Selected interior wall studs are being removed from the Brown Brothers Building following the stripping of drywall and stucco finishes.
Read moreAugust 17, 2025 • 600 Block
Truss inspections begin as crews remove the ceiling at 635 Cleveland Street.
Read moreAugust 16, 2025 • Peoples Bank
Chalk lines and spray paint are used to mark the wall locations at Peoples Bank, starting the framing work.
Read moreRestoration crews rebuilt the south parapet of the F.W. Woolworth Co. building, adding a continuous bonding beam and installing framing to support sheathing and stucco.
Read moreAugust 14, 2025 • 600 Block
Sound- and temperature-insulated plumbing is removed from the upstairs of 639 Cleveland Street.
Read moreAugust 13, 2025 • Brown Brothers
Crews remove several dozen second-floor wooden doors and frames not slated for restoration as part of the Brown Brothers Building transformation.
August 12, 2025 • Peoples Bank
Second-floor copper water lines are being installed at the Peoples Bank building with a press-fit system for secure, efficient connections.
Read moreAugust 11, 2025 • F.W. Woolworth Co.
Crews are removing selected storefront bricks from Woolworth to prepare for replacement masonry that blends seamlessly.
Read more