July 6, 2025 • F.W. Woolworth Co.
Crews remove the south parapet at the F.W. Woolworth Building to make way for a structural bond beam.
Read moreJune 30, 2025 • Peoples Bank
Crews reinforce the exposed west wall of the Peoples Bank building with concrete blocks and begin framing new utility corridors.
Grease traps installation completes beneath the ground-floor slab at the Peoples Bank building.
Read moreJune 19, 2025 • The Telephone Building
Mural installation completes on the east face of the historic Telephone Building to highlight Clearwater’s past and present.
Read moreJune 13, 2025 • Peoples Bank
The east wall of the Peoples Bank building is rebuilt using reinforced concrete blocks.
Read moreJune 4, 2025 • The Telephone Building
With interior window trim now in place, the Telephone Building’s first-floor storefront takes a step closer to completion.
Read moreCrews uncover a hidden steel vault during demolition at Woolworth and dismantle it over three days for safe removal.
Read moreThe Telephone Building awning is painted in Marsh Brown and Mink, designer-selected to match its original design. Primer and two coats ensure lasting durability.
Read more