October 13, 2026 • 600 Block
Workers are drilling into the existing column footings at 639 Cleveland Street to prepare connections for new wall footings. The drilled openings will allow the new foundations to tie into the existing structure, strengthening the building while providing support for new reinforced masonry walls. This work integrates the existing foundation elements with the new construction planned for the building.
Learn more about the redevelopment plans for the 600 block.
October 10, 2026 • 600 Block
October 9, 2026 • 600 Block
October 7, 2026 • 600 Block
October 5, 2026 • 600 Block
October 5, 2026 • 600 Block
October 3, 2026 • 600 Block
October 2, 2026 • 600 Block
See daily progress on Historic Cleveland Street