October 27, 2026 • 600 Block
At 639 Cleveland Street, crews are filling the first completed section of new masonry wall with concrete. After masons reached the initial wall height, reinforcing bars were placed within the hollow cells before concrete was pumped into the wall. Workers guide the hose and monitor placement as the cells are filled solid, creating reinforced masonry for the new wall.
Learn more about the redevelopment plans for the 600 block.