See daily progress on Historic Cleveland Street
June 23, 2025 • Brown Brothers
Crews remove demolition debris from the Brown Brothers Building, including wood, gypsum and plaster.
Read moreJune 15, 2025 • Peoples Bank
The elevator shaft at Peoples Bank was fully rebuilt with reinforced concrete block walls and a new foundation.
Read moreSecond-floor decking has been removed at the F.W. Woolworth Co. building, exposing joists and clearing the way for structural repairs to correct decades of uneven flooring.
Read moreCrews demolished the outdated east stairwell at the Woolworth building and poured a new foundation to begin reconstructing it with concrete blocks.
Read moreFinal paint work on the first floor of the Telephone Building brings the interior to completion, with all exposed beams now matched to the original color scheme.
Read moreNew underground plumbing has been installed at the Peoples Bank building, including piping for restrooms, clearing the way for slab preparations and future tenant-ready infrastructure.
Read moreCrews uncovered signs of a long-forgotten fire during interior demolition at 635 Cleveland Street, revealing burn marks and charred framing above the ceiling and on the walls.
Read moreMay 14, 2025 • The Telephone Building
Crews are hand-staining the birch doors on the first floor of the Telephone Building, as part of the detailed interior finish work that is bringing the 1915 landmark in line with its carefully restored historic façade.