May 23, 2025 • Peoples Bank
New underground plumbing has been installed at the Peoples Bank building to serve future first-floor commercial tenants. This phase includes piping for restrooms and a commercial-grade grease trap—both critical to supporting active use.
Using a mini excavator, crews dug precise trenches at key interior locations. Once excavation was complete, they installed new plumbing lines and prepared the system for grease trap placement.
This foundational work clears the way for slab preparation and concrete pouring, moving the restoration another step forward.
Learn more about the full restoration plan for the Peoples Bank.
March 1, 2026 • Peoples Bank
February 26, 2026 • Peoples Bank
February 24, 2026 • Peoples Bank
February 22, 2026 • Peoples Bank
February 20, 2026 • Peoples Bank
February 18, 2026 • Peoples Bank
February 16, 2026 • Peoples Bank
February 14, 2026 • Peoples Bank
February 12, 2026 • Peoples Bank
February 9, 2026 • Peoples Bank