Grease traps installation completes beneath the ground-floor slab at the Peoples Bank building.
Read moreJune 15, 2025 • Peoples Bank
The elevator shaft at Peoples Bank was fully rebuilt with reinforced concrete block walls and a new foundation.
Read moreJune 13, 2025 • Peoples Bank
The east wall of the Peoples Bank building is rebuilt using reinforced concrete blocks.
Read moreA portion of the roof at Peoples Bank was removed and replaced with angled planks and sheathing, both of which encourage proper stormwater drainage.
Read moreThe new elevator shaft is taking shape at the Peoples Bank, where block walls are reinforced with poured concrete for lasting support.
Read moreMay 28, 2025 • Peoples Bank
Crews are rebuilding a section of the east wall at Peoples Bank, reinforcing its foundation and preparing it to support key upper-level architectural elements.
Read moreNew underground plumbing has been installed at the Peoples Bank building, including piping for restrooms, clearing the way for slab preparations and future tenant-ready infrastructure.
Read moreCarpenters reinforced the interior structure of the Peoples Bank to preserve its framework as restoration continues.
Read moreMay 16, 2025 • Peoples Bank
Crews exposed sections of the foundation and slabs at Peoples Bank, reinforcing them with mesh and rebar as part of the ongoing renovation.
Read moreMay 12, 2025 • Peoples Bank
Crews complete vertical saw cutting into the east wall’s second-floor façade in preparation for upcoming demolition work.
Read moreCrews reconstruct the elevator pit at Peoples Bank, deepening and reinforcing the original foundation to support the new elevator shaft.
Read moreWith scaffolding in place, stucco demolition begins at the historic Peoples Bank. Crews are removing thick, outdated stucco to prepare for full façade restoration.
Read moreCrews demolish and prepare to rebuild the compromised east wall at the Peoples Bank, reinforcing the building’s stability while protecting the surrounding environment.
Read moreOur restoration team partnered with Boyd Clocks to carefully disassemble the historic 1930s clock at Peoples Bank. The copper-faced timepiece is now undergoing full restoration, including reglazing, cleaning and preservation of its patina.
Read moreApril 1, 2025 • Peoples Bank
Crews begin constructing new first-floor walls at Peoples Bank, setting the stage for continued restoration.
Read moreMarch 20, 2025 • Peoples Bank
Crews remove the aging roof and begin reinforcing the second floor of the historic Peoples Bank building.
Read moreFebruary 12, 2025 • Peoples Bank
Interior demolition at Peoples Bank removes nonoriginal finishes and systems, revealing the building’s original structure and layout as the foundation for restoration.
Read moreJanuary 28, 2025 • Peoples Bank
A high-rise crane removes the bulky elevator room from the Peoples Bank building, restoring its 1920s silhouette.
Read moreJanuary 24, 2025 • Peoples Bank
Excavator carefully removes a nonhistoric vault from the Peoples Bank building, restoring original floor space.
Read more