August 7, 2025 • Peoples Bank
Plumbers have started rough-in work on the second floor of the Peoples Bank, following the completion of underground lines. Crews are dry-fitting pipes and preparing for final connections.
Read morePeoples Bank crews finish the second layer of replacement plywood for the second-floor decking, preparing the space for new interior finishes.
Read moreJuly 30, 2025 • Peoples Bank
Concrete crews level the filled first-floor plumbing trenches at the Peoples Bank, sealing in new mechanical systems in preparation for the next stage of interior framing.
Read moreJuly 25, 2025 • Peoples Bank
With underground plumbing work complete, crews have begun trench preparation, installing mesh and rebar to ready the Peoples Bank for a concrete pour-back.
Read moreJuly 21, 2025 • Peoples Bank
Following two months of repair, the scaffolding and overhead protection at the historic Peoples Bank building has been removed, revealing its refreshed exterior and returning its full visual presence to Cleveland Street.
Read moreCrews complete second-floor decking repairs at the Peoples Bank building, leveling the trusses and installing new materials.
Read moreJuly 12, 2025 • Peoples Bank
Window bucks are being installed at the Peoples Bank building, setting the stage for new windows as part of the ongoing restoration.
Read moreJuly 8, 2025 • Peoples Bank
Crews complete critical wall preparation at the Peoples Bank Building, covering the brick face with mortar in advance of waterproofing and stucco installation.
Read moreCrews pour a concrete slab around the installed grease traps at the Peoples Bank building, completing another key step in the building’s infrastructure work.
Read moreJune 30, 2025 • Peoples Bank
Crews reinforce the exposed west wall of the Peoples Bank building with concrete blocks and begin framing new utility corridors.
June 25, 2025 • Peoples Bank
Structural steel installation is completed inside the historic Peoples Bank building, reinforcing the structure.
Read moreGrease traps installation completes beneath the ground-floor slab at the Peoples Bank building.
Read moreJune 15, 2025 • Peoples Bank
The elevator shaft at Peoples Bank was fully rebuilt with reinforced concrete block walls and a new foundation.
Read moreJune 13, 2025 • Peoples Bank
The east wall of the Peoples Bank building is rebuilt using reinforced concrete blocks.
Read moreA portion of the roof at Peoples Bank was removed and replaced with angled planks and sheathing, both of which encourage proper stormwater drainage.
Read moreThe new elevator shaft is taking shape at the Peoples Bank, where block walls are reinforced with poured concrete for lasting support.
Read moreMay 28, 2025 • Peoples Bank
Crews are rebuilding a section of the east wall at Peoples Bank, reinforcing its foundation and preparing it to support key upper-level architectural elements.
Read moreNew underground plumbing has been installed at the Peoples Bank building, including piping for restrooms, clearing the way for slab preparations and future tenant-ready infrastructure.
Read moreCarpenters reinforced the interior structure of the Peoples Bank to preserve its framework as restoration continues.
Read moreMay 16, 2025 • Peoples Bank
Crews exposed sections of the foundation and slabs at Peoples Bank, reinforcing them with mesh and rebar as part of the ongoing renovation.
Read more