September 3, 2025 • Peoples Bank
Metal framing is installed around the structural beams at the Peoples Bank building, adding strength and preparing the walls for upcoming finishing procedures.
Read moreSeptember 1, 2025 • Peoples Bank
Boyd’s Clocks secured the historic clock brackets to the Peoples Bank, ensuring long-term stability for the landmark feature.
August 28, 2025 • Peoples Bank
Crews at the Peoples Bank building completed electrical installation by placing junction and outlet boxes on new framing.
Read moreAugust 24, 2025 • Peoples Bank
Plumbing crews installed a cast-iron storm drainage system at the Peoples Bank building, ensuring reliable water runoff management for the restored landmark.
Read moreAugust 20, 2025 • Peoples Bank
Metal framing crews are making rapid progress at the Peoples Bank building, with wall structures taking shape on both the first and second floors.
Read moreAugust 16, 2025 • Peoples Bank
Chalk lines and spray paint are used to mark the wall locations at Peoples Bank, starting the framing work.
Read moreAugust 12, 2025 • Peoples Bank
Second-floor copper water lines are being installed at the Peoples Bank building with a press-fit system for secure, efficient connections.
Read moreAugust 7, 2025 • Peoples Bank
Plumbers have started rough-in work on the second floor of the Peoples Bank, following the completion of underground lines. Crews are dry-fitting pipes and preparing for final connections.
Read morePeoples Bank crews finish the second layer of replacement plywood for the second-floor decking, preparing the space for new interior finishes.
Read moreJuly 30, 2025 • Peoples Bank
Concrete crews level the filled first-floor plumbing trenches at the Peoples Bank, sealing in new mechanical systems in preparation for the next stage of interior framing.
Read moreJuly 25, 2025 • Peoples Bank
With underground plumbing work complete, crews have begun trench preparation, installing mesh and rebar to ready the Peoples Bank for a concrete pour-back.
Read moreJuly 21, 2025 • Peoples Bank
Following two months of repair, the scaffolding and overhead protection at the historic Peoples Bank building has been removed, revealing its refreshed exterior and returning its full visual presence to Cleveland Street.
Read moreCrews complete second-floor decking repairs at the Peoples Bank building, leveling the trusses and installing new materials.
Read moreJuly 12, 2025 • Peoples Bank
Window bucks are being installed at the Peoples Bank building, setting the stage for new windows as part of the ongoing restoration.
Read moreJuly 8, 2025 • Peoples Bank
Crews complete critical wall preparation at the Peoples Bank Building, covering the brick face with mortar in advance of waterproofing and stucco installation.
Read moreCrews pour a concrete slab around the installed grease traps at the Peoples Bank building, completing another key step in the building’s infrastructure work.
Read moreJune 30, 2025 • Peoples Bank
Crews reinforce the exposed west wall of the Peoples Bank building with concrete blocks and begin framing new utility corridors.
June 25, 2025 • Peoples Bank
Structural steel installation is completed inside the historic Peoples Bank building, reinforcing the structure.
Read moreGrease traps installation completes beneath the ground-floor slab at the Peoples Bank building.
Read moreJune 15, 2025 • Peoples Bank
The elevator shaft at Peoples Bank was fully rebuilt with reinforced concrete block walls and a new foundation.
Read more