June 29, 2026 • 600 Block

Curved Entryway Preparation Advances at 629–633 Cleveland Street

Workers cut canopy wall during canopy demolition.
Crews cut through the canopy wall at 629 Cleveland Street as dust rises from the demolition work along the roofline.

At 629–633 Cleveland Street, crews have completed removal of the existing canopy, exposing the underlying roofing layers and steel framing that once supported it. The work clears the storefront for the next phase of construction: a new curved entryway designed to give the building a more distinctive street presence.

Crews remove canopy wall above exposed roof framing.
Crews work from the roof deck at 629–633 Cleveland Street, removing the remaining canopy wall and exposing the steel framing.

Learn more about the full renovation plan for the 600 block.