January 30, 2025 • F.W. Woolworth Co.
A welder reinforces a historic steel column in the subfloor of the Woolworth building, part of a major foundation restoration phase.
Thirty-two original structural steel columns were excavated, assessed and repaired—reforming the core strength of the Woolworth building from the ground up.
Restoration crews uncovered and restored these original steel columns at the heart of the Woolworth building. Each was excavated from decades of concrete encasement, evaluated by structural engineers and reinforced where needed.
Repairs included welding in new steel plates and repouring the surrounding floor slab using 70 cubic yards of concrete. These foundational upgrades enhance the long-term stability of the historic structure.
The restored columns now serve both a functional and symbolic role—supporting the building’s future while honoring its past. Learn more about the full restoration plan for the F.W. Woolworth Co. building.
May 7, 2025 • F.W. Woolworth Co.
May 1, 2025 • F.W. Woolworth Co.
March 18, 2025 • F.W. Woolworth Co.
December 2, 2024 • F.W. Woolworth Co.