September 17, 2025 • Peoples Bank
Roofing crews at the Peoples Bank building have advanced to the detailing stage of installation. With the roofing membrane in place, roofers are now focusing on accessories that secure the system and protect vulnerable areas.
This includes covers and protective strips along the roof’s edges to create a watertight seal. Crews are also installing an access walking mat to provide easy access to amenities while protecting the roof from damage. These details extend the life of the roof and are important steps toward completing the building’s roofing system.
Learn more about the full restoration plan for the Peoples Bank building.