See daily progress on Historic Cleveland Street
July 17, 2025 • 600 Block
Crews remove all fiberglass insulation from 639 Cleveland Street as part of the full interior demolition, clearing the way for sustainable material upgrades in the building’s renovation phase.
Read moreJuly 13, 2025 • 600 Block
Crews remove the floor tile at 623 Cleveland Street to expose the subfloor and allow for detailed architectural assessments ahead of interior layout design.
Read moreJuly 9, 2025 • 600 Block
Crews remove ceramic floor tile at 635 Cleveland Street, exposing the underlying concrete slab in preparation for finish work.
Read moreJuly 5, 2025 • 600 Block
Crews remove the back structure and all of the remaining studs at 635 Cleveland Street.
Read moreJune 26, 2025 • 600 Block
Crews remove all non-load-bearing studs inside 639 Cleveland Street, preparing for new framing and future renovations.
Read moreJune 17, 2025 • 600 Block
All bathrooms and plumbing systems are removed at 635 Cleveland Street, clearing the way for installation of new copper plumbing.
Read moreAfter extensive interior demolition, the lead architect conducted a full walkthrough of the 600 Block to document exposed structural features and finalize the restoration plans.
Read moreDemolition crews uncover a heavy safe inside 645 Cleveland Street, dating back to the early 1900s and adding a new layer of discovery to the ongoing renovation.
Read more