Metal framing is installed around the structural beams at the Peoples Bank building, adding strength and preparing the walls for upcoming finishing procedures.

Read more
MORE PHOTOS

Original bricks are being reset into Woolworths front parapet with fresh mortar, bringing the parapet back to its historical proportions.

Read more
MORE PHOTOS

Boyd’s Clocks secured the historic clock brackets to the Peoples Bank, ensuring long-term stability for the landmark feature.

Read more
MORE PHOTOS

The kitchen hood and ductwork at 635 Cleveland Street have been removed, preparing the space for renovation.

Read more
MORE PHOTOS

Restoration continues at the Woolworth Building as crews remove parapet bricks by hand and set them aside for reuse.

Read more
MORE PHOTOS

Crews are clearing away demolition debris into a 30-yard dumpster at the Brown Brothers Building.

Read more
MORE PHOTOS

Crews at the Peoples Bank building completed electrical installation by placing junction and outlet boxes on new framing.

Read more
MORE PHOTOS

Crews completed installation of roof decking at the Woolworth building, replacing trusses and preparing for an upgraded roof system.

Read more
MORE PHOTOS

Restoration of the Brown Brothers Building uncovers original brick walls on the second floor.

Read more
MORE PHOTOS

Structural truss removal marks a major interior demolition milestone in the renovation of 635 Cleveland Street.

Read more
MORE PHOTOS

Plumbing crews installed a cast-iron storm drainage system at the Peoples Bank building, ensuring reliable water runoff management for the restored landmark.

Read more
MORE PHOTOS

Crews remove the north-side lath-and-plaster walls on the second floor of the Brown Brothers Building, revealing an earlier construction method tougher than drywall.

Read more
MORE PHOTOS

Wooden trusses are lifted by crane and secured atop the Woolworth building, preparing the structure for decking and installation of a durable waterproof roof.

Read more
MORE PHOTOS

Crews removed sections of brick at 635 Cleveland Street to examine the building’s integrity, revealing structural concerns that require stabilization.

Read more
MORE PHOTOS

Metal framing crews are making rapid progress at the Peoples Bank building, with wall structures taking shape on both the first and second floors.

Read more
MORE PHOTOS

Masons have laid concrete block and begun installing the brick façade on the Woolworth building, ensuring it matches the historic appearance of the structure.

Read more
MORE PHOTOS

Selected interior wall studs are being removed from the Brown Brothers Building following the stripping of drywall and stucco finishes.

Read more
MORE PHOTOS

Truss inspections begin as crews remove the ceiling at 635 Cleveland Street.

Read more
MORE PHOTOS

Chalk lines and spray paint are used to mark the wall locations at Peoples Bank, starting the framing work.

Read more
MORE PHOTOS

Restoration crews rebuilt the south parapet of the F.W. Woolworth Co. building, adding a continuous bonding beam and installing framing to support sheathing and stucco.

Read more
An exciting new chapter of historic restoration begins for four unique properties on Cleveland Street in Downtown Clearwater.
See the magnificent transformation now underway