August 21, 2026 • 600 Block
Brick and concrete block are being separated and removed from sections of the existing front wall as preparation work continues at 623–627 Cleveland Street.
Read moreAugust 20, 2026 • 600 Block
Following trench excavation, crews are beginning installation of the underground plumbing system that will support the renovated building.
Read moreExcavation work begins behind 629–633 Cleveland Street as crews prepare trenches for new underground plumbing.
Read moreAugust 18, 2026 • 600 Block
Newly opened masonry channels at 623–627 Cleveland Street receive steel reinforcing bars as crews prepare the walls for the next stage of construction.
Read moreAugust 17, 2026 • 600 Block
Masons rebuild the back wall at 623–627 Cleveland Street with new concrete masonry units, restoring the structure to its planned configuration.
Read moreAugust 16, 2026 • 600 Block
The next phase of interior preparation continues at 623–627 Cleveland Street as crews trench the slab for underground plumbing.
Read moreWorkers remove masonry between existing wall cuts at 623–627 Cleveland Street, creating vertical channels to prepare the structure for the next phase of redevelopment work.
Read moreAugust 14, 2026 • 600 Block
Structural preparation continues at 623–627 Cleveland Street as crews create reinforcement channels within the existing masonry walls.
Read moreAugust 13, 2026 • 600 Block
The removal of existing floor materials is revealing the underlying conditions at 635 Cleveland Street as site preparation moves forward.
Read moreAugust 12, 2026 • 600 Block
Controlled demolition continues at 623–627 Cleveland Street as crews clear existing concrete elements to prepare the foundation area for future work.
Read moreAugust 11, 2026 • 600 Block
Masons install new lintels above wall openings at 629–633 Cleveland Street while rebuilding surrounding concrete block to integrate the structural supports.
Read moreAugust 10, 2026 • 600 Block
Temporary forms come down at 629–633 Cleveland Street as crews patch infill openings and finish the newly reinforced concrete masonry walls.
Read moreAugust 9, 2026 • 600 Block
Selective slab removal at 623–627 Cleveland Street prepares the building frontage for a new façade configuration and recessed storefront entry.
Read moreThe removal of existing masonry columns opens the frontage of 623–627 Cleveland Street and clears the way for the next phase of improvements.
Read moreThe walls at 629–633 Cleveland Street are becoming solid-filled structural assemblies as crews carefully control the concrete placement.
Read morePlywood forms enclose exposed sections of the concrete masonry walls at 629–633 Cleveland Street, creating secure areas for the upcoming concrete placement.
Read moreSite preparation continues on the 600 block as crews remove the existing concrete slab at 645 Cleveland Street, creating a clear path for future construction.
Read moreAugust 4, 2026 • 600 Block
Heavy equipment clears existing concrete footings at 645 Cleveland Street, preparing the site for the next phase of redevelopment within the 600 block.
Read moreDemolition crews clear masonry debris at 639 Cleveland Street, preparing the site for reconstruction with updated materials and modern building standards.
Read moreAugust 2, 2026 • 600 Block
Careful demolition work is underway as selected wall sections are removed to prepare 629–633 Cleveland Street for the next phase of construction.
Read more