See daily progress on Historic Cleveland Street
Truckloads of concrete debris leave the 600 block site as crews advance preparations for reconstruction. The work marks another step toward bringing new retail, dining and service spaces to downtown Clearwater.
Read moreJune 22, 2026 • 600 Block
Inspections behind the 600 block focus on utility poles that will be temporarily removed during redevelopment activities.
Read moreJune 21, 2026 • 600 Block
Contractors begin removing aging roofing materials and roof decking at 623–627 Cleveland Street, marking another step in the building’s renovation.
Read moreJune 20, 2026 • 600 Block
Site preparation continues on the 600 block with floor slab demolition underway at 635 Cleveland Street.
Read moreJune 18, 2026 • 600 Block
The removal of the existing overhang clears the way for the planned transformation of 623–627 Cleveland Street.
Read moreMay 5, 2026 • 600 Block
Pedestrian pathways on the 600 block are cleared of existing pavers to prepare for cleaning and restoration.
Read moreThe 600 block continues its major phase of demolition, opening each property for new construction.
Read moreLarge-format graphics are installed along the 600 block construction fencing, presenting a cohesive visual preview of the redeveloped Cleveland Street corridor.
Read moreApril 29, 2026 • 600 Block
Materials are cut, cleared and consolidated as 635 Cleveland Street transitions from demolition into its next phase.
Read moreApril 27, 2026 • 600 Block
Crews remove masonry and wall sections along the rear of 635 Cleveland Street, exposing underlying structural elements for reconstruction.
Read moreApril 25, 2026 • 600 Block
Interior and exterior demolition are underway at 629–633 Cleveland Street, clearing the way for a rebuilt storefront system.
Read moreApril 23, 2026 • 600 Block
Exterior demolition progresses as storefront systems are cleared at 625–627 Cleveland Street.
Read moreApril 22, 2026 • 600 Block
Knee wall demolition at 629–633 Cleveland Street opens the storefront, improving visibility from the street level and creating a more accessible interior layout.
Read moreSeptember 19, 2025 • 600 Block
From panels to conduits, all outdated electrical has been stripped from 635 Cleveland Street.
Read moreSeptember 16, 2025 • 600 Block
High-ceiling drywall removal reveals roof trusses at 635 Cleveland Street.
Read moreSeptember 14, 2025 • 600 Block
Crews remove foam insulation from the ceiling at 635 Cleveland Street, exposing roof trusses.
Read moreSeptember 12, 2025 • 600 Block
Environmental concerns guided the removal of refrigerant before the vents and ductwork were demolished at 635 Cleveland Street.
Read moreSeptember 4, 2025 • 600 Block
The interior floor slab at 635 Cleveland Street is demolished and removed to clear the ground floor.
Read moreAugust 31, 2025 • 600 Block
The kitchen hood and ductwork at 635 Cleveland Street have been removed, preparing the space for renovation.
Read moreAugust 25, 2025 • 600 Block
Structural truss removal marks a major interior demolition milestone in the renovation of 635 Cleveland Street.
Read more