June 23, 2025 • Brown Brothers
Crews remove demolition debris from the Brown Brothers Building, including wood, gypsum and plaster.
Read moreJune 22, 2025 • F.W. Woolworth Co.
Restoration teams clear a steel truss from the Woolworth building’s second floor, removing a major obstacle to interior leveling.
Read moreCrews remove the outdated tile floor inside 629 Cleveland Street, setting the stage for upcoming renovation work.
Read moreGrease traps installation completes beneath the ground-floor slab at the Peoples Bank building.
Read moreJune 19, 2025 • The Telephone Building
Mural installation completes on the east face of the historic Telephone Building to highlight Clearwater’s past and present.
Read moreJune 18, 2025 • F.W. Woolworth Co.
At the Woolworth building, steel frames are being installed to support a new historically styled, hurricane-rated storefront system.
Read moreJune 17, 2025 • 600 Block
All bathrooms and plumbing systems are removed at 635 Cleveland Street, clearing the way for installation of new copper plumbing.
Read moreJune 16, 2025 • Brown Brothers
Crews remove the interior walls at the Brown Brothers Building to reveal the original framework.
Read moreJune 15, 2025 • Peoples Bank
The elevator shaft at Peoples Bank was fully rebuilt with reinforced concrete block walls and a new foundation.
Read moreJune 14, 2025 • The Telephone Building
Crews complete careful brick repairs on the first floor of the Telephone Building by reusing original white brick from hidden sections and replacing damaged areas to preserve both structure and character.
Read moreJune 13, 2025 • Peoples Bank
The east wall of the Peoples Bank building is rebuilt using reinforced concrete blocks.
Read moreJune 12, 2025 • 600 Block
During interior demolition at 635 Cleveland Street, crews removed old carpet, exposing the concrete slab beneath.
June 11, 2025 • F.W. Woolworth Co.
At the Woolworth building, crews pour a new elevator pit foundation, creating a solid base for a code-compliant shaft.
The interior storefront of the Brown Brothers Building has been removed, opening space for a newly designed entry system as part of ongoing renovations.
Read moreJune 9, 2025 • The Telephone Building
A duct is added to the first-floor AC at the Telephone Building to help reduce noise and create a quieter space for future tenants.
Read more
Crews removed the old carpet from 629 Cleveland Street, uncovering the original tile floor beneath as part of early stage demolition.
A portion of the roof at Peoples Bank was removed and replaced with angled planks and sheathing, both of which encourage proper stormwater drainage.
Read moreJune 6, 2025 • F.W. Woolworth Co.
Crews have begun leveling the second floor in preparation for the installation of a new floor system at the Woolworth building.
Read moreJune 4, 2025 • The Telephone Building
With interior window trim now in place, the Telephone Building’s first-floor storefront takes a step closer to completion.
Read more
AC coils were removed at 639 Cleveland Street and refrigerant was recovered at 645, completing an environmentally responsible phase of demolition.