See daily progress on Historic Cleveland Street
The interior structure at 639 Cleveland Street continues to evolve as demolition crews clear existing elements for future work.
Read moreJuly 30, 2026 • 600 Block
Crews remove structural stair connections inside 639 Cleveland Street, separating existing steel components as interior demolition prepares the building for redevelopment.
Read moreJuly 29, 2026 • 600 Block
Another visible milestone takes shape on the 600 Block. At 639 Cleveland Street, east wall removal creates new views into the building.
Read moreCrews remove a concrete column from the front façade of 639 Cleveland Street, clearing the structure for continued redevelopment and future improvements.
Read moreJuly 26, 2026 • 600 Block
Demolition findings at 629–633 Cleveland Street reveal hidden wall conditions, leading to targeted reinforcement work that strengthens the building’s future structure.
Read moreYears of patched and deteriorated concrete are being removed as the Peoples Bank Building restoration continues to transform the streetscape.
Read moreJuly 20, 2026 • 600 Block
A crane-assisted operation removes a concealed 45-foot steel beam from the 639 Cleveland Street façade, advancing demolition and preparing the building for its next phase of work.
Read moreCrews at 639 Cleveland Street have exposed the existing metal decking after removing the previous roof materials, allowing the team to prepare the surface for the next phase of roof installation.
Read moreFaçade demolition at 639 Cleveland Street reveals a concealed steel support beam, documenting original construction methods.
Read moreJuly 9, 2026 • 600 Block
Preparations continue inside 639 Cleveland Street as crews install structural shoring before the next phase of demolition.
Read moreJuly 8, 2026 • 600 Block
Professional surveyors are documenting the 600 block’s topography and underground utilities, providing the precise site data needed to advance the next phase of redevelopment.
Read moreJuly 7, 2026 • 600 Block
Crews are stabilizing 623–627 Cleveland Street with temporary shoring, creating a safe foundation for the next phase of construction.
Read moreJuly 6, 2026 • 600 Block
Forklifts, trucks and neatly stacked masonry units show the 600 block moving steadily through its renovation sequence.
Read moreJuly 3, 2026 • 600 Block
Crews remove sections of the concrete floor slab at 629–633 Cleveland Street to prepare for underground plumbing installation.
Read moreJuly 2, 2026 • 600 Block
Utility trenching preparations are underway at 629–633 Cleveland Street.
Read moreContractors remove aging utility light poles from the rear parking areas of the 600 block, clearing the site and supporting ongoing demolition and redevelopment activities.
Read moreRemoval of the existing canopy at 629–633 Cleveland Street reveals former structural layers and prepares the storefront for its new curved entryway.
Read moreJune 26, 2026 • 600 Block
The front façade at 623–627 Cleveland Street is being carefully cleared for the next stage of work.
Read moreJune 26, 2026 • 600 Block
Visible progress continues on the 600 block: the roof at 629–633 Cleveland Street has been opened up for full replacement.
Read moreJune 25, 2026 • 600 Block
Roof deck removal clears the way for new decking and a watertight roof membrane at 623–627 Cleveland Street.
Read more