See daily progress on Historic Cleveland Street
December 14, 2025 • F.W. Woolworth Co.
Painters applied the final dark green coat to the Woolworth Building’s southwest entryway, completing the historically inspired finish around the windows and doors.
Read moreDecember 13, 2025 • F.W. Woolworth Co.
Crews installed new period-style windows along the west side of the Woolworth building, securing each unit and sealing them for long-term protection.
Read moreDecember 12, 2025 • F.W. Woolworth Co.
Crews installed golden door hardware on the southwest entry of the Woolworth building, adding another detail that supports the building’s 1930s-inspired restoration.
Read moreDecember 11, 2025 • Peoples Bank
The Peoples Bank building’s Mediterranean Revival tile design is being mapped across the east façade.
Read moreDecember 10, 2025 • F.W. Woolworth Co.
The removal of west-side windows marks another step in the Woolworth building restoration.
Read moreDecember 9, 2025 • F.W. Woolworth Co.
Crews prepared the Woolworth building’s southwest entryway for paint by completing trim, sealing gaps and creating an even surface for the upcoming finish.
Read moreDecember 8, 2025 • F.W. Woolworth Co.
Detailed door framing work continues inside the Woolworth building.
Read moreDecember 7, 2025 • F.W. Woolworth Co.
A shipment of dark-stained, period-appropriate doors arrives at the Woolworth building, bringing the restoration one step closer to completion.
Read moreDecember 6, 2025 • F.W. Woolworth Co.
Crews installed a white membrane roof on the northwest awning facing Cleveland Street, adding a reflective “cool roof” surface above the future restaurant entrance.
Read moreDecember 5, 2025 • F.W. Woolworth Co.
Crews are laying flooring upstairs in the Woolworth building, installing floor planks, cutting edge pieces for a clean fit and creating a durable surface for future use.
Read moreDecember 4, 2025 • F.W. Woolworth Co.
Crews install dark wood wainscoting in the Woolworth building lobby, adding 1930s-inspired detail to the restored interior.
Read moreDecember 3, 2025 • Peoples Bank
Carpenters completed building the east staircase frame at the Peoples Bank building.
Read moreDecember 2, 2025 • F.W. Woolworth Co.
A key cooling component is now in place as crews connect the indoor AC unit at the Woolworth building.
Read moreDecember 1, 2025 • F.W. Woolworth Co.
Restoration continues at the Woolworth building with trim added to the southwest entry.
Read moreNovember 30, 2025 • Peoples Bank
Chalk lines now mark the layout for the mosaic tile façade at the Peoples Bank building.
Read moreNovember 29, 2025 • F.W. Woolworth Co.
Guide rails and wiring are being set as the Woolworth building elevator installation moves forward.
Read moreNovember 28, 2025 • F.W. Woolworth Co.
Awning specialists installed the southwest awning frame at the Woolworth building.
Read moreNovember 27, 2025 • F.W. Woolworth Co.
Electrical crews install and test all first floor outlets at the Woolworth building, connecting wiring, securing fixtures and completing final safety checks.
Read moreNovember 26, 2025 • Peoples Bank
Carpenters are forming the structural base of the Peoples Bank building east staircase with fresh lumber and precision cuts.
Read moreNovember 25, 2025 • F.W. Woolworth Co.
New paint and trim detailing now highlight the Woolworth building’s historic sign and façade.
Read more