See daily progress on Historic Cleveland Street
December 23, 2025 • F.W. Woolworth Co.
New lobby signage adds both function and craftsmanship to the Woolworth building interior.
December 22, 2025 • Peoples Bank
Street-level progress continues with storefront doors installed at the Peoples Bank building.
Read moreDecember 21, 2025 • Peoples Bank
Work continues on the Peoples Bank building as steel ledges prepare the façade for mosaic tiles.
Read moreDecember 20, 2025 • F.W. Woolworth Co.
Interior spaces become more complete as ceiling tiles go in at the Woolworth building.
Read moreDecember 19, 2025 • F.W. Woolworth Co.
Final paint preparation brings the Woolworth building storefront closer to its finished look.
Read moreDecember 18, 2025 • Peoples Bank
Crews craned new air-conditioning units onto the roof of the Peoples Bank building, marking a major milestone in the building’s mechanical upgrades.
Read moreDecember 17, 2025 • F.W. Woolworth Co.
Drywall and mudding work reintegrates the windows back into the Woolworth building interior.
Read moreDecember 16, 2025 • F.W. Woolworth Co.
Brass hardware is now in place on the Woolworth building storefront doors.
Read moreDecember 15, 2025 • Peoples Bank
Concrete floor preparation is underway at the Peoples Bank building where the east storefront will be installed.
Read moreDecember 14, 2025 • F.W. Woolworth Co.
Painters applied the final dark green coat to the Woolworth Building’s southwest entryway, completing the historically inspired finish around the windows and doors.
Read moreDecember 13, 2025 • F.W. Woolworth Co.
Crews installed new period-style windows along the west side of the Woolworth building, securing each unit and sealing them for long-term protection.
Read moreDecember 12, 2025 • F.W. Woolworth Co.
Crews installed golden door hardware on the southwest entry of the Woolworth building, adding another detail that supports the building’s 1930s-inspired restoration.
Read moreDecember 11, 2025 • Peoples Bank
The Peoples Bank building’s Mediterranean Revival tile design is being mapped across the east façade.
Read moreDecember 10, 2025 • F.W. Woolworth Co.
The removal of west-side windows marks another step in the Woolworth building restoration.
Read moreDecember 9, 2025 • F.W. Woolworth Co.
Crews prepared the Woolworth building’s southwest entryway for paint by completing trim, sealing gaps and creating an even surface for the upcoming finish.
Read moreDecember 8, 2025 • F.W. Woolworth Co.
Detailed door framing work continues inside the Woolworth building.
Read moreDecember 7, 2025 • F.W. Woolworth Co.
A shipment of dark-stained, period-appropriate doors arrives at the Woolworth building, bringing the restoration one step closer to completion.
Read moreDecember 6, 2025 • F.W. Woolworth Co.
Crews installed a white membrane roof on the northwest awning facing Cleveland Street, adding a reflective “cool roof” surface above the future restaurant entrance.
Read moreDecember 5, 2025 • F.W. Woolworth Co.
Crews are laying flooring upstairs in the Woolworth building, installing floor planks, cutting edge pieces for a clean fit and creating a durable surface for future use.
Read moreDecember 4, 2025 • F.W. Woolworth Co.
Crews install dark wood wainscoting in the Woolworth building lobby, adding 1930s-inspired detail to the restored interior.
Read more