See daily progress on Historic Cleveland Street
January 17, 2026 • F.W. Woolworth Co.
Interior finishing continues at the Woolworth building with baseboards added to future tenant spaces.
Read moreThe Woolworth building’s lobby showcases a new period photo, bringing a piece of history into the restored space.
Read moreJanuary 5, 2026 • F.W. Woolworth Co.
Attention to detail continues inside the F.W. Woolworth building with final refinements to the woodwork.
Read moreJanuary 2, 2026 • F.W. Woolworth Co.
The final stages of the interior restoration include mudding and smoothing the walls at the Woolworth building.
Read moreDecember 31, 2025 • F.W. Woolworth Co.
The Woolworth building’s interior now features newly installed brass drinking fountains.
Read moreDecember 29, 2025 • F.W. Woolworth Co.
Solid wood bathroom doors, partitions and 1930s-style hardware are now installed inside the Woolworth building, reinforcing the restored interior’s historic character.
Read moreDecember 27, 2025 • F.W. Woolworth Co.
Interior décor at the Woolworth building now includes framed scenes from its early retail days.
Read moreDecember 25, 2025 • F.W. Woolworth Co.
Exterior lighting installation brings a finished look to the Woolworth building’s storefront.
Read moreDecember 23, 2025 • F.W. Woolworth Co.
New lobby signage adds both function and craftsmanship to the Woolworth building interior.
December 20, 2025 • F.W. Woolworth Co.
Interior spaces become more complete as ceiling tiles go in at the Woolworth building.
Read moreDecember 19, 2025 • F.W. Woolworth Co.
Final paint preparation brings the Woolworth building storefront closer to its finished look.
Read moreDecember 17, 2025 • F.W. Woolworth Co.
Drywall and mudding work reintegrates the windows back into the Woolworth building interior.
Read moreDecember 16, 2025 • F.W. Woolworth Co.
Brass hardware is now in place on the Woolworth building storefront doors.
Read moreDecember 14, 2025 • F.W. Woolworth Co.
Painters applied the final dark green coat to the Woolworth Building’s southwest entryway, completing the historically inspired finish around the windows and doors.
Read moreDecember 13, 2025 • F.W. Woolworth Co.
Crews installed new period-style windows along the west side of the Woolworth building, securing each unit and sealing them for long-term protection.
Read moreDecember 12, 2025 • F.W. Woolworth Co.
Crews installed golden door hardware on the southwest entry of the Woolworth building, adding another detail that supports the building’s 1930s-inspired restoration.
Read moreDecember 10, 2025 • F.W. Woolworth Co.
The removal of west-side windows marks another step in the Woolworth building restoration.
Read moreDecember 9, 2025 • F.W. Woolworth Co.
Crews prepared the Woolworth building’s southwest entryway for paint by completing trim, sealing gaps and creating an even surface for the upcoming finish.
Read moreDecember 8, 2025 • F.W. Woolworth Co.
Detailed door framing work continues inside the Woolworth building.
Read moreDecember 6, 2025 • F.W. Woolworth Co.
Crews installed a white membrane roof on the northwest awning facing Cleveland Street, adding a reflective “cool roof” surface above the future restaurant entrance.
Read more