See daily progress on Historic Cleveland Street
February 16, 2026 • Peoples Bank
Interior infrastructure progresses at the Peoples Bank building with continued heating and air conditioning work.
Read moreFebruary 14, 2026 • Peoples Bank
Second-floor interiors at the Peoples Bank building become more defined with ongoing floor tile installation.
Read moreFebruary 12, 2026 • Peoples Bank
A long-missing architectural element returns as Mediterranean mosaic tiles arrive at the Peoples Bank building.
Read moreFebruary 9, 2026 • Peoples Bank
Interior restoration continues at the Peoples Bank building with heating and air conditioning installation underway.
Read moreFebruary 7, 2026 • Peoples Bank
Interior restoration continues at the Peoples Bank building with second-floor ceramic tile dry-fit underway.
Read moreFebruary 5, 2026 • Peoples Bank
Black-and-white ceramic floor tiles arrive at the Peoples Bank building, reflecting classic 1930s design.
Read moreFebruary 2, 2026 • Peoples Bank
Second-floor interior work advances at the Peoples Bank building as the final self-leveling concrete pour is completed.
Read moreJanuary 31, 2026 • Peoples Bank
Interior progress continues at the Peoples Bank building with second-floor lighting installation underway.
Read moreJanuary 29, 2026 • Peoples Bank
Templates mark the future footprint of key exterior elements at the Peoples Bank building.
Read moreJanuary 27, 2026 • Peoples Bank
Drywall work begins on the first floor of the Peoples Bank building, with crews measuring and laying out the interior spaces.
Read moreJanuary 26, 2026 • Peoples Bank
A water-resistant coating is applied to the Peoples Bank building as part of ongoing exterior restoration.
Read moreJanuary 24, 2026 • Peoples Bank
A clock restoration specialist completes preparation work at the Peoples Bank building to support the return of its historic clock.
Read moreJanuary 22, 2026 • Peoples Bank
First-floor pipe insulation marks the next phase of interior restoration at the Peoples Bank building.
Read moreJanuary 20, 2026 • Peoples Bank
Ceiling framing on the second floor of the Peoples Bank building begins to define future office and tenant spaces.
Read moreJanuary 18, 2026 • Peoples Bank
Fire-resistant specialty glass has been installed in the west wall window openings of the Peoples Bank building, marking another restoration milestone.
Read moreJanuary 16, 2026 • Peoples Bank
Insulation work continues at the Peoples Bank building, supporting long-term preservation of historic materials.
Read moreJanuary 14, 2026 • Peoples Bank
Metal support brackets are being installed inside the west wall window openings at the Peoples Bank building in preparation for specialty glass installation.
Read moreJanuary 13, 2026 • Peoples Bank
Another architectural feature takes shape as canopy preparations begin at the Peoples Bank building.
Read moreJanuary 12, 2026 • Peoples Bank
Progress continues at the Peoples Bank building with the arrival of large, specialty glass panels for the west wall.
Read moreJanuary 10, 2026 • Peoples Bank
Framing and drywall work are underway on the first floor of the Peoples Bank building, beginning to define the interior layout as restoration continues.
Read more